Burghley Tower – Fire Risk Assessment Upgrade

Value: £511,000
Client: Ealing Homes
Duration:24 weeks

Fire risk assessment upgrade works to communal areas of a twelve storey block of 94 no. occupied flats.

Works included:

-Replacement of flat entrance doors and communal entrance doors connected to each flat.

-New electronic door entry system to main entrance doors connected to each flat.

-New dividing screens on each floor.

-Installation of new Automatic Opening Ventilators on each floor, connected to new fire alarm panels.

-Design and installation of new emergency lighting scheme and new communal lighting.

-Fire-proofing to floor voids and service risers.

-Asbestos removal.

-Class ‘O’ coatings to communal walls and ceilings.

-New floor coverings to communal areas and non-slip coatings to stairs.