Our Projects

Queens Park Court

Value: £633,000
Client: City West Homes
Duration: 20 weeks

Major fire and electrical upgrade works to communal areas within 9no. 1950’s built blocks of flats on the Queens Park Court Estate, London W10, complimented by complete internal redecoration.

Works included:

  • Replacing existing communal front doors and frames with FD60S door sets
  • Fire alarm and detection system upgrade
  • New door entry system with key fob control
  • Replacement communal and emergency lighting and containment
  • Replace existing hoppers with fire rated and certified Hardall SPC/RS hoppers
  • Window repairs
  • Class O’ decorations to communal walls and ceilings (Integra Coatings) and decoration to all previously painted surfaces 

Resident and Leaseholder engagement was key to achieving critical works sequencing and completion on time (and on budget).